21-032 Subaqueous Sewer Force Main Replacements (Crossings) - ITB
Bid/RFP Status:
Awarded
Bid/RFP Due Date:
Friday, April 23, 2021 - 2:00pm
Bid Awarded To:
Accurate Drilling Systems, Inc.
Bid/RFP Reference Number:
21-032 Subaqueous Sewer Force Main Replacements (Crossings) - ITB
Designer/Engineer:
Weston & Sampson
Estimated Budget/Cost Estimate:
$1,829,331.00
Engineer's Estimate:
2.6M
PROJECT DESCRIPTION/ SCOPE OF WORK:
The work on this contract consists of the installation sanitary sewer force main through directional drilling and open cut installation. The work is split into two separate alignments: one that travels under Gordon River and one that travels under Rock Creek.