DESCRIPTION OF WORK
1. This Section pertains to the replacement of electrical equipment at the CITY of Naples
(CITY) WWTP located at 1400 3rd Avenue North in Naples, Florida. The equipment to
be replaced is Switchgear #1 (SWITCHGEAR) and Motor Control Centers (MCC’s)
MCC-3 and MCC-4.
2. The SWITCHGEAR replacement project and the MCC replacement project are
independent, however, a single contract shall be awarded to the CONTRACTOR for
the replacement of both the SWITCHGEAR and the MCC’s.
3. The MCC replacement project shall be completed prior to the start of the
SWITCHGEAR replacement project due to equipment downtime limitations and
equipment lead times.